How Close Were We To Blackouts Yesterday?

We received an Octopus energy alert for a Saving Session lunch time yesterday the 8th Jan.

Hey Alastair,

The first Saving Session of January is today between 5-6pm!

Yesterday was cold with no wind and light snow over the UK. 

As Paul Homewood on his site summarises a post from Watt Logic:

Yesterday saw a blackout near miss in what turned out to be the tightest day the GB electricity market has seen since 2011. Wind power was 2.5 GW through the evening peak, solar was (obviously) zero and there were significant interconnector outages leaving expected capacity at just 5.7 GW. Had just one large power station tripped this evening, demand control would have been a real prospect.

The Operator of the Grid – NESO issued an alert saying that things are getting risky,

An ELECTRICITY MARGIN NOTICE has been issued by the National Energy System Operator to encourage market actions to increase System Margins. For the period: from 16:00 hrs to 19:00 hrs on Wednesday 08/01/2025 There is a reduced system margin. System margin shortfall 1700 MW The current contingency requirement is 1000 MW. 300 MW of generation is excluded from the available system margin due to system constraints.

Octopus then rushed out a Savings in an attempt to cut demand during the critical period 5-6PM.

What actually heppened:

On 5 January, NESO published its peak demand forecast for 8 January at 43.267 GW. Generator availability was expected to be 47.425 GW, and interconnector availability 6.674 GW. The operational planning margin requirement was 3.235 GW, meaning the surplus was 0.923 GW.

At 8am on 8 January, peak demand for the evening peak forecast by Amira to be 48.6 GW – this is intended as a true GB electricity demand forecast accounting for the effects of embedded generation in the distributions networks. At the time, the NESO transmission system demand forecast was 46.777 GW (at 17:00). The Initial Transmission System Demand Outturn data from BMRS indicated that actual transmission system demand was 46.825 GW (at 17:30) ie the forecast was too low.

This is highly worrying to the country and has not been widely reported. It does look like we are heading into a Train Wreck of low production, limited capacity excess while demand is increasing as move EV’s hit the road and more Heat Pumps are added. YOu have been warned. 

Share:

More Posts

iphone 16

Latest iPhone Success Is A First For Apple

Apple takes #1 spot in Q1 2025 for Smart Phone Sales Research for Counterpoint shows that the global smartphone market grew by 3% in the first quarter of 2025, driven by growth in emerging markets and “a subsidy-led demand boost in China,” it said.  The research went on to mention the thing that has never

Macan EV Turbo front

Review: 2025 Porsche Macan EV Turbo – Electric PowerED SUV Meets Porsche DNA

Macan Turbo EV The wait is over. Porsche has finally pulled the wraps off the all-electric Macan EV Turbo, and after spending some time behind the wheel, it’s clear: this isn’t just a Macan with a battery. It’s the future of Porsche’s compact SUV — and it’s everything we hoped for. First Impressions Let’s get

tranmission lines

Gas-fired power generation hits four-year high

It was the dunkelflaute Low levels of renewable generation and high demand drove gas-fired power generation to its highest level since 2021 for the first quarter of the year. That was the standout highlight in a new report on the British power generation market by Montel Analytics. Montel’s study showed that electricity generated by combined

macan ev

Porsche Sales up in USA and Down in China

Porsche records robust results for 2024 Robust 2024 financial year: Group sales revenue of 40.1 billion euros, Group Operating profit of 5.6 billion euros, Group operating return on sales of 14.1 per cent. Strong net cashflow almost reaches record levels of 2023. Proposed dividend amount the same as previous year. Negative effects from market developments